05.06.2019

Snagging East Germany

Vestas, Various, 50-100 turbines

Blades

Click to share
FacebookLinkedInTwitter

Description:
The FairWind Blades department was tasked with full scope repair of blades and towers at 17 Vestas sites in Germany.

 

  • Work was incredibly diverse, with different repairs and maintenance required at each site.
  • The type of turbine and project varied from site to site.
  • Tasks were technically challenging, requiring specialist knowledge.

 

FairWind was able to meet this comprehensive and diverse set of challenges by employing 17 teams of specialized technicians.

 

The experience, certification, and training of the FairWind blades personnel is some of the highest in the industry, with only a handful of teams existing in the world that can operate at this level.

 

The snags were completed within 6 months.

 

 

Download Case Study
Project Name:
Snagging East Germany
Project Type:
Blades
Customer:
Vestas
Location:
Germany
Execution Period:
April 2018 to July 2018
Scope:
Full scope snagging, blade and tower repair & maintenance