Description:
Wind farm situated near the village of Nichel near the highway on the Belin-Lipsk route. The execution was carried out in two stages. In the first part, from August 2021 to October 2021, we built 4 turbines and worked in two shifts. In the second part, after a 4-month break, we also built 4 turbines, but in one shift. The whole project was completed in the second half of March 2022