Description

FairWind took on the Installation of 22 Siemens Gamesa
6.6-170 T165 turbines, each with eight tower sections.

  • Pre-assembly to final installation
    was completed within a timeframe of
    six months
  • Two shift operations for installation and
    one shift for internal finishing
 

Results

  • Efficient execution of the pre-assembly and installation process
  • Maintained safety and quality standards throughout the project
  • Successfully completed phase one of the installation within the scheduled timeframe.
 

Read more here or contact us for service type.

More case studies

FairWind technicians performing offshore wind turbine blade repair as part of a renewable energy maintenance operation
Offshore structural blade repair
Wind turbine operations at the Silver Star Wind Farm in North America, supported by FairWind
Maintenance and overhaul of Avanti lift systems
Siemens turbine onshore installation project
en_GBEN