Description

FairWind took on the Installation of 22 Siemens Gamesa
6.6-170 T165 turbines, each with eight tower sections.

  • Pre-assembly to final installation
    was completed within a timeframe of
    six months
  • Two shift operations for installation and
    one shift for internal finishing
 

Results

  • Efficient execution of the pre-assembly and installation process
  • Maintained safety and quality standards throughout the project
  • Successfully completed phase one of the installation within the scheduled timeframe.
 